This is our 1st overseas project in Cambodia. We have been appointed by the Owner to provide strengthening design for the 28-storey foundation system supported on bored piles.
The existing bored pile foundation work which had been completed by the design & build contractor unable to achieve the required proposed design pile working load during pile testings. About 50% pile cap were also completed at that time.
Here’s a look at the overall site condition when we first arrived at the site. Our journey begins…